  • A new and significant California Court of Appeal decision that will have substantial financial impacts on direct contractors, their sureties, and subcontractors was published on April 17, 2020, called Crosno Construction, Inc. v. Travelers Casualty and Surety Company of America.  This case, which focuses on “pay-when-paid” language in a public works subcontract, substantially impacts the timing of a payment bond surety’s obligation to the subcontractor, and has the potential to be applied to the timing for payment by a general (direct) contractor to a subcontractor.  In essence, this case holds that a “pay-when-paid” provision in a subcontract is void and unenforceable against a subcontractor’s payment bond claim when the provision purports to delay payment for as long as necessary for the direct contractor to pursue its claim against the project owner.    

     

    It is well-settled that “pay-if-paid” clauses are unenforceable as contrary to public policy in California pursuant to the landmark California Supreme Court decision in Wm. R. Clarke Corp. v. Safeco Ins. Co. (1997) 15 Cal.4th 882.  In that case, the Supreme Court distinguished an unenforceable pay-if-paid provision from a pay-when-paid provision, by explaining that a pay-when-paid provision does not establish a true condition precedent, but “merely [fixes] the usual time for payment to the subcontractor, with the implied understanding that the subcontractor in any event has an unconditional right to payment within a reasonable time.”  Wm. R. Clarke, supra, 15 Cal.4th at p. 885 (emphasis added).   Subsequent to the Wm. R. Clarke case, general contractors throughout the State of California amended their form subcontract agreements so that the parties would agree to the definition of what constitutes a “reasonable time.”  In most sophisticated subcontract agreements, that “reasonable time” is defined as the length of time it takes the general contractor to pursue its remedies against the owner.

     

    In Crosno, the general contractor (Clark Bros., Inc.) used that now-commonplace language, requiring the subcontractor (Crosno Construction) to wait a “reasonable time” for payment if Clark was not paid by the owner, and defining what a “reasonable time” meant.  Specifically, the subcontract contained the following pay-when-paid provision in the event the public entity owner delayed making payments to Clark:

     

    “If Owner or other responsible party delays in making any payment to Contractor from which payment to Subcontractor is to be made, Contractor and its sureties shall have a reasonable time to make payment to Subcontractor.  ‘Reasonable time’ shall be determined according to the relevant circumstances, but in no event shall be less than the time Contractor and Subcontractor require to pursue to conclusion their legal remedies against Owner or other responsible party to obtain payment, including (but not limited to) mechanics’ lien remedies.”

     

    In accordance with the subcontract, Crosno was almost finished with the fabrication, erection, and coating of two 250,000-gallon welded steel water reservoir tanks for a public work of improvement when Crosno was ordered to suspend work after a dispute had arisen between Clark and the public entity and, the next day, served a stop payment notice on the public entity.  Approximately 45 days later, Crosno made a claim upon Clark’s payment bond and provided notice of such claim to Travelers. After Travelers denied the payment bond claim as premature by invoking the pay-when-paid provision in Crosno’s subcontract, Crosno filed suit to enforce its stop payment notice and claim on the payment bond.  Roughly one year later, Crosno filed a motion for summary judgment/adjudication as to its payment bond cause of action against Travelers, arguing that the pay-when-paid provision in the subcontract was void and unenforceable.  The trial court agreed and granted Crosno’s motion, awarding judgment in the amount of $562,435 in favor of Crosno and against Travelers, plus almost 3 ½ years of interest on that amount, in addition to attorneys’ fees. 

     

    The Fourth Appellate District of the California Court of Appeal affirmed the trial court’s summary judgment in favor of Crosno.  The appellate court, “agree[ing] with the trial court’s sound analysis,” held that the pay-when-paid provision in the Crosno subcontract, which delayed the subcontractor’s right to payment for an indefinite time period until the general contractor’s litigation against the owner concluded, “would unreasonably affect or impair [the subcontractor’s] statutory payment bond remedy (Civil Code section 8122) and is unenforceable for the same reasons expressed in Wm. R. Clarke….” 

     

    The appellate court rejected Travelers’ argument that section 8122 was not implicated because the pay-when-paid clause only set the time for payment and did not waive Crosno’s bond rights.  Emphasizing that California’s statutory scheme devoted to resolution of payment disputes on construction projects protects against both waiver and impairment of payment rights, the court held that the definition of a “reasonable time” set forth in the subcontract provision at issue includes an indefinite time frame that is unreasonable.  The court highlighted several times that while a pay-when-paid provision “might properly allow payment to be delayed for a reasonable period of time after completion of work, enforcing the provision here ‘does not provide for payment within a reasonable time.’”  Invoking this particular pay-when-paid provision to delay Travelers’ obligation under the payment bond until an undetermined time in the future when Clark’s litigation with the public entity concluded “would unquestionably and unreasonably affect or impair Crosno’s right to recover under the payment bond without either an express waiver or full payment required by [Civil Code] sections 8124 and 8126.  Accordingly, the specific pay-when-paid provision before us is ‘void and unenforceable’ (§§ 8122, 8126) against Crosno’s payment bond claim.” 

     

    It should be noted that a key fact in this case was that there was no dispute regarding whether Crosno was entitled to payment.  The only issue was timing.  When a claim (bond or otherwise) involves the determination of entitlement to payment, the surety or direct contactor will have defenses to payment.  The court stated that its decision “does not…allow subcontractors whose work is disputed to recover from [a] surety before merit is finally determined by the owner and the general contractor.”  Therefore, if Crosno’s work had been implicated in Clark’s dispute with the public entity, Traveler’s obligation would not have been triggered until liability had been resolved. 

     

    In sum, the key to the court’s decision was the particular language used in the subcontract, which defined a “reasonable time” as an unreasonable indefinite period.  The court determined that such a definition was unacceptable because that provision “has the effect of the delaying payment to the subcontractor for what may be—and in this case was—an unreasonably long period of time.”  And while this case concerned a payment bond claim and the surety’s obligations, the court’s reasoning seems easily translatable to a subcontractor’s claim against a direct contractor.  Therefore, as a result of the Crosno case, not only will sureties not be able to rely on unreasonable definitions of “reasonable time” for payment, but also direct contractors should amend their subcontract form agreements to redefine a “reasonable time” as something that is not indefinite and unreasonably long

     

    For more information please contact the following partners of the firm’s construction law practice group:

     

    Sara H. Kornblatt 

    skornblatt@gibbsgiden.com

    (310) 734-3391

    Sara H. Kornblatt is an equity partner whose practice is concentrated in both the development and management of construction projects as well as handling claims and complex litigation matters. She is skilled in drafting and negotiating bid and contract documents for owners, contractors, and subcontractors, and handling bid protest and subcontractor substitution issues for both public entity owners and bidders.

     

    Richard J. Wittbrodt

    rwittbrodt@gibbsgiden.com

    (310) 734-3397

    Richard J.Wittbrodt is an equity partner of the firm. His primary emphasis is in construction litigation, including prosecuting and defending claims of delay, disruption, defective construction, mechanics lien and stop notice foreclosure actions, for both public and private projects. Mr. Wittbrodt has experience representing large general contractors with multi-million dollar complex hospital construction cases involving OSHPD, delay, design  issues, breach of contract, warranty of plans and specifications, prompt payment requirements, contract interpretation issues, and lost profits.

     

    Christopher E. Ng

    cng@gibbsgiden.com

    (310) 734-3367

    Christopher Ng is an equity partner, executive committee member, and the managing partner of Gibbs Giden. Chris primarily represents companies in a wide range of business, commercial and construction negotiations and disputes. Chris is nationally recognized in the field of construction law and regularly pens articles and contributes to treatises for construction industry professionals and other lawyers.

     

    The content contained herein is published online by Gibbs Giden Locher Turner Senet & Wittbrodt LLP (“Gibbs Giden”) for informational purposes only, may not reflect the most current legal developments, verdicts or settlements, and does not constitute legal advice. Do not act on the information contained herein without seeking the advice of licensed counsel. For specific questions about any of the content discussed herein or any of the content posted to the Gibbs Giden website please contact the article attorney author or send an email to info@gibbsgiden.com. The transmission of information by email, over the Gibbs Giden website, or any transmission or exchange of information over the Internet, or by any of the included links is not intended to create and does not constitute an attorney-client relationship. For a complete description of the terms of use of this information and the Gibbs Giden website please see the Website Terms section at https://www.gibbsgiden.com/website-terms/. This publication may not be reproduced or used in whole or in part without written consent of the firm. Copyright 2020 Gibbs Giden Locher Turner Senet & Wittbrodt LLP ©